Logo: TechTrax...brought to you by MouseTrax Computing Solutions

Microsoft Project: 13 - Costs

by Mike Glen, MVP

This month we’ll have a closer look at setting up costs.

Not An Accounting Package

I do not have any financial training and I’m grateful to those who have a better insight than me, so I’ve dragged phrases out of the newsgroups to summarize what Project isn’t and cannot do.

First and foremost, Microsoft Project is NOT an accounting package. It is not intended to give, and it does not provide, the facilities to do detailed accounting or financial management. It will not provide cost-accounting, pay-roll figures, or the tracking of inventory costs, overhead costs, salaries, or inflation costs. It does not handle Purchase Orders, Change Orders, Asset Requests, Approvals, Purchase Orders Invoices, payments and retentions, and is rotten at keeping track of money to the level of accuracy you need for making payments. It is not interested in profit, revenues, payables, receivables, time-and-billing, professional fees and it does not track Vendors or Vendor Contracts. All these are facets of accounting and time-and-billing programs. Managing the overall costs of employment of a resource is a job for accounting applications, not project management applications and Microsoft Project is no different. It is not concerned with the costs to the company of the resource doing anything else other than the specific project tasks.

So what does it do? Well, Project is a critical path scheduling tool and oriented to scheduling and managing work, not finances. The costs in Project are bottom-up budgets - predictions of what something will cost, not top-down limits on how much you're allowed to spend. It does cost estimating and tracking, but that is only for budgeting and progress tracking purposes. All it is concerned with is the direct costs of getting the deliverables within the specific project done and has no direct provision for overheads and other costs of doing business.

Resource Costs

Let’s start with setting up some resource costs. Create a new project starting on 31 May 04 (discard the old Garden project we were using last time as it will probably still have non-standard calendars set up) and enter a task “Make Terraces” with 10 days Duration. Now assign Fred to that task. Check from a split screen that he is assigned 80 hours of Work. Double-click Fred’s name (although you can double-click on a resource’s name in many views, like the Resource Sheet, that show the resource name) and in the resulting Resource Information dialog, click on the Costs tab. Click in the first Standard Rate cell, enter “20” and press Return. Project will show the per hour rate.

The currency shown is that selected in Tools/Options.../View tab, where you can enter a default currency. However, you can have only one currency per project.

Having entered 20, when you press Return, the “£” (or whatever you have set up) and “/hr” will automatically be inserted for you, and the cursor will drop down to the next cell, ready for another entry. Equally, if Fred was paid by the week or year, then you will have to enter, say, 500/w or 20000/y – try it!

Standard Rate

Ah! But what is the Standard Rate, did I hear you say? Well, it should not be solely his wages, but the cost to the project of using this man. It should include his wages, training costs, holidays, pension scheme, etc, i.e. whatever it costs the company to use this man on this project compared to whatever else he could be doing to earn money for the company. These figures should be obtained from the company’s accounting department. Many companies produce a series of equivalent, rationalised or equalised wages to cover a variety of employees – use these costs as your “standard”. Remember you’re not using a cost-accounting system, but inputting figures on which you can budget and track the project’s costs.

Now, these rates are used by Project to calculate the cost of each task on which Fred is employed. Project will calculate by the minute ( actually by 1/10th of a minute, irrespective of the units entered in the Standard Rate cell) to arrive at £1600 (£20/hour * 80 hours). You can see the resulting task Total Cost from the Gantt Chart view, then View/Table: Entry/Cost.

The Cost tab allows profiling of the resource’s cost. The Effective Date will show “- -“ if the resource is available at the start of the project, otherwise it will show the first date on which he is available. Profiling allows Project to take into account changes in costs as time goes by.

Suppose Fred has a 5% increase in wages from 7 Jun 04, enter that and when you press Return, Project will calculate the new rate as £21/h.

And take that into account for the task’s costs (5 days to 6 Jun at £20/h = £800 and another 5 days from 7 Jun at £21/h = £840) which now total £1640.

You can also check costs from the Gantt Chart view: split the screen, right-click in the lower pane and select Resource Cost.

 

Costs can be applied by project at the beginning or end of the task, or spread evenly throughout the task (prorated). In the Resource Information dialog, click the drop-down arrow in the Cost accrual: box and select from the pick list.

A total of 25 different rate levels can be applied to allow for cost changes with time. In each, standard, overtime and per use (e.g. a machine might cost £1000 per use) rates can be entered. In addition, if resources will work on various tasks that require different base rates (e.g. a different rate for on-site working and another for in-office working), up to five different base rates can be assigned in tabs A to E for each resource so that the correct rate for each task assignment can be selected. From the Resource Usage view, double-click on the Terraces task to bring up the Assignment Information dialog. Here you can select the appropriate Cost rate table from the pick list.

Overtime

Overtime costs will be accounted for provided work is entered as overtime. Project does not automatically calculate additional hours as overtime unless they are specifically assigned as overtime work. Assignment is made in the Resource Work form viewed from a split Gantt chart screen, by right-clicking and selecting.

Type the number of overtime hours for each resource in the Ovt. Work field. The amount of overtime work specified does not get added to the amount of work for the task. Work always represents the total amount of work. Overtime work merely represents the portion of the total amount of work that should be considered and costed as overtime work. For instance, if a person works 10 hours, which includes 8 hours of regular work and 2 hours of overtime work, assign Work at 10 hours and overtime work at 2 hours, not work at 8 hours and overtime work at 2 hours. Project spreads the amount of overtime evenly over the span of the assignment. Try not to plan to use overtime as this is one of the few tools a project manager has to catch up on a task that's running late - overtime should be used as an emergency facility, not as part of the original plan.

You will then need to put a value into the Overtime Rate cell (usually at a higher rate than the standard of £20: say, time-and-a-half would be £30/h), otherwise overtime will be free! Remember, this is the cost to the company of the overtime work, not necessarily the cash that Fred will get.

 

Material Costs

To enter material costs that are based on a unit price, assign a Per-use cost to a material resource before assigning this resource to a task. When specifying how many units to be used, Project will calculate the total material cost by multiplying the base unit price by the number or percentage of units specified.

Fixed Costs

Finally, we can see from the Costs table that we were looking at earlier in the Gantt Chart view, that there is a facility to enter Fixed Costs – this is the only place you can enter these. Let’s say that the Make Terraces task requires the purchase of old railway sleepers at a cost of £200. Then enter that figure in the Fixed Cost cell. Notice that the task Total Cost  increases by that amount to £1993. If you have a summary task, Fixed Costs are not rounded up although they are added into the Total Cost field. This allows you to place a Fixed Cost on a summary task, for example, the garden designer’s fee for the project could be entered into the Fixed Cost cell for the project summary task.

Next Month 

Next month we’ll have a more detailed look at customizing fields.

Click to rate this article.

 

Go up to the top of this page.

This site powered by the Logical Web Publisher™: Content management by Logical Expressions, Inc.