Logo: TechTrax...brought to you by MouseTrax Computing Solutions

Microsoft Project: 2 - Entering Task Data

by Mike Glen, MVP

I hope those of you who are following these beginner's hints and tips have tried out my introductory guide to network analysis at: http://www.mvps.org/project/networkanalysis.htm. As a result, I hope you've been playing with Microsoft Project and maybe started on the Tutorial contained within Project. This month I will concentrate on entering the basic task data into Project.

Firstly, let's look at the opening screen so that we can become familiar with its layout and terminology. Although there will be some detailed differences depending on your version of Project (this picture is from Project 2000), the basics are identical with the exception of the View bar which was introduced into Project 2000, and a Project Guide which appears down the left side of the Table in Project 2002.

The Project Opening Screen

Image of Projects opening screen.

Working Area of the Screen
The main working area of the screen is in two main parts: the Entry table on the left and the Gantt chart [named after the U.S. engineer H. L. Gantt (1861-1919)] on the right, separated by a divider bar.

Entry Table
The entry table will hold a listing of every task required by the project and will show calculated details for each task.

Gantt Chart
The Gantt chart will show bars drawn to represent the time span of each task against a calendar timescale.

Divider Bar
The vertical parallel lines forming the divider bar can be moved to the right to show more columns in the table or to the left to show more of the Gantt chart. Hovering the mouse over the bar will invoke a left-right arrow: click and drag to move the bar, and double-click to dock the divider bar neatly to the nearest column edge.

Entering Data

Image of the data entry area in Project.

Entry Bar
Enter a task and the text also appears in the entry bar. Click on the tick or press enter to accept, or click the X to cancel. Edit by selecting a field and clicking the text that appears in the entry box, or by pressing F2 and it will be available for editing. Data can also be edited within the cell. Project will give the task an identification number (ID) of 1, fill in a default duration of 1 day?, show a 1-day bar on the Gantt chart and move the cursor down to highlight the next task cell. Data can also be edited within the cell.

Entering Durations
Project assumes the duration is 1 day? The question mark (introduced in Project 2000) indicates that this is an estimated or uncertain duration, and clicking on the duration cell can alter this. Enter the duration required as a number followed by a letter code and ? if you wish to retain the uncertainty indication. [Note: Months were introduced in Project 2000.]

m
= min = minute em = elapsed minute
h
= hr = hour eh = elapsed hour
d
= dy = day ed = elapsed day
w
= wk = week ew =elapsed week
mo
= mon = month emo =elapsed month
y
= yr = year ey =elapsed year

A question mark can also be entered to indicate the duration is estimated or tentative Alternatively, use the Spin Control by clicking on the up arrow to increase the duration and the down arrow to reduce. Elapsed duration is the amount of time a task will take to finish, based on a 24-hour day and a 7-day week, including holidays and other nonworking days. [Note that elapsed times should only be used for inanimate (material) resources or for tasks that are independent of resources, eg., concrete curing or paint drying.] Any changes will appear in the entry bar—click the Tick to stay in that cell, press the Enter key or press the down arrow key to accept and move the cursor down to the next field. The duration of a month defaults to mean 20 working days, but this can be changed in Tools/Options/Calendar tab.

Milestones
To create a milestone, enter zero duration.


Outlining
Project allows representation of a Work Breakdown Structure (WBS) in that it allows outlining. When outlining the tasks in a project schedule, it is organised so the structure of the project can be seen, making the schedule easier to manage. Outlining can:

  • Arrange tasks in a hierarchical structure so it can be seen how subtasks fit within broader groups of tasks called summary tasks.

  • Identify the major phases of the project with summary tasks.

  • Use either a top-down (enter summary tasks first) or bottom-up (enter subtasks first) approach to building the schedule.

  • Display only the summary tasks for the project.

  • Create reports that include subtasks, summary tasks, or both.

  • Display the project using a task numbering system called a Work Breakdown Structure (WBS).

A task is moved to a lower level by indenting or demoting it. A summary task is created by demoting the task directly following it (in the order of task ID numbers). A task can be moved to a higher level by outdenting or promoting it, unless it is already at the highest level.

Select Project/Outline… or click on the appropriate tool button to indent or outdent. A Summary task will then appear bold (black) and have outline symbols beside the task name. A - (minus sign) indicates that the summary is expanded, i.e., all the subtasks are showing at the next level. Clicking on the - sign will close down the summary so that only the summary bar is showing (note the missing task ID numbers). It will then sport a + sign, that can be clicked to reverse the process. Similar + and - signs are available in the Formatting toolbar. Greater choice of the levels to be revealed can be selected from the pick list invoked from the Show tool button, introduced with Project 2000—earlier versions have a double-plus button to show them all.

Manipulating Gantt Bars

Task Selection
In the Gantt chart, move the mouse pointer over the centre of a Gantt bar, and the pointer will turn into a 4-way arrow. An information box will appear to aid selection of the correct task.


Changing the Start Date
When the 4-way arrow appears, click and hold down the left mouse button and drag left or right and an information box will show the Start and Finish dates. These dates will change as the bar is dragged, leaving the duration the same—release the button when satisfied. A constraint indicator will appear in the Indicator column: hover the mouse pointer over the indicator to read constraint details.


Note! Resist changing start or finish dates by typing in the data or by manipulating the bars with the mouse, as this will cause a constraint date to be imposed thus losing flexibility. Make sure that was what was intended.

If the new start date coincides with a non-working day, a Planning Wizard will allow the option to Move the task to the next working day or Make the non-working day into a working day. As with most Wizards, there is an option to prevent further activation of this Wizard by clicking the box Don't tell me about this again. In doing so Project will assume the first (default) setting will apply to any subsequent occasions.

If, however, the new start date is near to the end of an adjacent Gantt bar, another Wizard will allow the option to Link them or to Move the task without adding a link. If linking is allowed, then no constraint will be set, as the predecessor will drive its start date.

Changing the Duration
To change the duration of a task, move the mouse pointer the right end of a Gantt bar and the pointer will turn into a right-pointing arrow. Click and drag to the right and an information box will show the Finish date and Duration that will change to reflect the lengthening of the bar.

To Indicate Progress
Move the mouse pointer the left end of a Gantt bar and the pointer will change into a % right-pointing arrow. Click and drag to the right and an information box will show the Complete Through date.

The Complete Through date will change to reflect the percentage duration completed and will show as a black bar within the task bar.

Click and drag from the right end of the progress mark will allow editing. When progress or actual data has been entered, moving the pointer to the left end of the bar will turn the pointer to a left-pointing arrow, allowing the start date to be changed to reflect reality.

Splitting Tasks
Tasks can be split to show breaks in the schedule. Click on the Split Task tool button in the Standard toolbar, then click on the appropriate part of the Gantt bar and drag to the right. Tasks can be split many times. To remove the split, click on a split section to the right of the first section and drag to the left until the gap closes.

Next Month
Next month we will have a look at the logic linking and manipulating data. Have fun!

 

 

Go up to the top of this page.
This site powered by the Logical Web Publisher™: Content management by Logical Expressions, Inc.