By now you should be up and running with the basics of Microsoft Project. We
will now start to look into the more detailed and sophisticated aspects of Project
concerning the manipulation of Information and Calendars.
In many instances, double-clicking on a field, Gantt bar,
calendar date, network diagram task, links,
column headings, etc, will provide either a drop-down menu
or a dialog box of information.
Double-click on a task, right-click on a task and select
Task Information …,
select Project > Task Information…, Shift+F2, or click the
Information tool
button.

A tabbed Task Information dialog box will appear where information on the selected
task can be added or edited. Selecting a summary will give a dialog for Summary
Task Information. Pre-selecting multiple tasks will invoke a Multiple Task Information
dialog that will be blank, and data entered will be applied to all the selected
tasks. In this way, you can make global changes, provided there is a field in
Task Information dialog. Choose the appropriate tab for the type of information
to view or enter.
NOTE. Although you can enter new data in the fields shown, in the main you
should treat this as Project allowing you to look at information on what you
have selected. Resist the temptation to change data until you know the consequences
of your actions. For example, entering Start or Finish dates is generally not
a good idea, as this action will create Constraints which will limit the flexibility
of your project. As you have seen, the Start date is defined by the
Finish date
of its predecessor, and the Finish date is calculated by Project based on the
Duration you have estimated. Let Project do what it is designed to do - calculate
dates to show you what is possible.

In the General tab, you have the options of viewing or entering %Complete (for
tracking progress) and Priority (for telling Project which task gets overallocated
resources when levelling). If you don’t want the task bar to appear in the
Gantt
chart, you may select that action. Selecting "Roll up Gantt bar to summary"
will overlay the task bar on its summary task. Selecting both these actions
will show only the summary with the task bar superimposed on its bar – useful
for showing milestones in a high level report.
Details of Predecessors and Resources can be viewed, entered or edited in the
appropriate tab, whose appearance is similar to the familiar Entry Form of a
split screen.
Advanced Tab
The Advanced tab allows the viewing, entering or editing of a Deadline,
Constraint type and date, Task Type, the Effort
Driven setting, and applying a Calendar
and WBS code. Here is the place to create a constraint as a deliberate act –
use the pick lists to select the Constraint type: and Constraint
Date:. More
of these in later months.

A
note
can be attached to a task by selecting the
Notes
tab in the
Task Information
dialog box, or
Project
>
Task Notes…, or
Right-click
on a task and select
Task Notes, or
click
on the
Attach Notes
tool button.

The
Task Information
dialog box will appear with the
Notes
tab already selected.
The white area is a simple word processor in which text can be entered, edited
or formatted and objects (like a chart, diagram, picture, etc)
pasted.

Once a note has been written, a
Notes
indicator will appear in the indicator
field for that task.

Hovering the mouse pointer over the
indicator
will reveal the beginning of
the note.
Task
notes can be entered and edited from any view that shows the
task name. There are separate note fields for resources that can be accessed
from most views that show resources.
Resource Information
Resource information and notes can be entered and edited in a similar way to
that for
Task
Information. To activate,
double-click
the name of a resource shown in the
Resource Sheet
view or any view that shows resource names with the exception of the
Gantt
chart
view.
The
Resource Information
dialog allows the viewing, entering or editing of
resource availability,
working times
and
cost rates
which I’ll cover in a later
lesson. There is also a
Notes
tab which is identical in layout and operation
to that for
Task Notes, though this is for resource information like listing
qualifications, etc.

General Tab
In the
General
tab, you can enter
Workgroup
details like an
Email address
used
for communicating within a
Workgroup. You can identify the
Resource
type as
a
Material
resource or
Work
Resource
(usually meaning human!). You can use the
Group
and
Code
fields for whatever purpose you chose: eg management, programmers,
bricklayers, or pay code, employee number, etc, allowing you to sort or filter
using these fields. You can also indicate the
Availability
of the resource (a
sort of resource contour). This will allow for arrivals and departures from
the project for individual resources and to allow the
Units
available to be
changed for a pool type of resource or if a resource has a part time role. Enter
the date (use the drop-down calendar) and change the
Units
appropriately
Working Hours
If you plan to change the
working hours
from Project’s default, it is essential
to set them up correctly, ideally before entering any task data. It is worth,
therefore going into a little more detail. The settings can be seen and changed
in
Tools
>
Options
(where all Project’s defaults are set – more another day)
and select the
Calendar
tab.

The values for the
working
week
or
day
affect the way project views your entries
in the duration field. If, in the task
Duration
field, you type in 1 week, Project
looks to the setting you've made to define the number of hours (and thus man-hours)
that a week contains. Similarly for the
working
day. Equally, if you don't specify
a time, a task starts at the default setting of 08:00, and if you schedule from
the finish, tasks will end at the default of 17:00, both leaving the
Duration
to determine the other date. So, set these times first. Remember that it is
best to do this before entering any data as changes to
Tools
>
Options
generally
apply to the future entry of data and not what has already been entered. Hence,
it's a good idea to set the defaults in a "New Project" template (more another
day).
To schedule your project
working time
properly, you must also change the values in
Tools
>
Change Working Time.

Project calls the default working time the
Standard (Project Calendar). This
is set to working from Monday to Friday, 0800 hrs to 1700 hrs, 40 hours a week.
So, to define a working day, select all the days in the calendar week by click
and dragging across the calendar headings (M,T,W,Th F) so they are all highlighted.
(Doing this will also highlight every working day in every year throughout from
1984 to 2049.) Now on the right hand side, click in the
working hours
setting
and change the figures to meet your working day requirements.
To make a weekday nonworking (eg a national holiday): select the day(s) concerned
and then the
Nonworking
time
box. To change a default nonworking day (Saturdays
and Sundays) into a working day select the day(s) concerned and then the
Nondefault
working time
box. To change working hours for individual day(s), select and
then click and edit the
From:
and
To:
fields. Note that a night shift has to be set in one day, ie from midnight to cease work and then from start work to
midnight.
Resource Calendars
In the
Resource Information
dialog, click the
Working Time
tab and you will
see a
Change Working Time dialog, identical to the
Standard
calendar you have
just set up, with the Resource’s name already applied. Make appropriate changes
and click on OK. Note that the
Options…
button will go to
Tools> Options > Calendar
tab so that equivalence can be checked.
Task calendars
were introduced into Project 2000. If one or more tasks are
to be scheduled only on certain days or within certain hours (for example, scheduling
equipment maintenance after hours) a task calendar can be assigned to those
tasks. Create a
New
calendar and then assign the calendar to a task by picking
the calendar name in the
Calendar
field on the
Advanced
tab of the
Task
Information
dialog box. An indicator is used to flag those tasks that have a task calendar.
Recurring tasks, typically meetings, can be selected from
Insert
>
Recurring
Task…
to open the
Recurring Task
Information
dialog. The
Frequency
of the meeting
and its Duration
can be specified precisely. (Note that the
Duration
of the
Recurring Task's summary task
measures from the start of the first meeting to the end of the last meeting, and
thus has little relevance.) Beware of assigning resources to
Recurring Tasks
as it may cause overallocations that become difficult to resolve
and could well extend the end date of the project. For short meetings it might
be best to accept the absence of the resource at a meeting, or perhaps assign
at zero units.
Next Month
I think that’s enough for this month. Next month we’ll have a look at the basic
outputs of reports and printing.
|