|
Last month we had a look at the
assignment of multiple resources. This month we’ll see the effect of changing
the Task Type settings.
Effort
Driven – Task Type
By now, you will be getting
sick of my repetition of the effort driven formula:
Resource
Units X Duration = Work
I make no apologies, as it
needs to be engraved in the brain so that whatever you do with resources
you will automatically take the formula into account. Remember, the values
in the formula are set up for each task when a resource is first
assigned; subsequent changes will be governed by the formula.
As I mentioned last month,
there are several places in Project where you assign resources, but as with
multiple resources on one task, you need a view that shows all the relevant
parameters. If you want to investigate and use the different settings that
can be made to the Tasks, you need a view where all the parameters
are shown. Again, I always recommend using the same split screen technique
as we used last month. Using the same example for a project, make a garden
with an initial plan that includes a pool of Gardeners. Make it start on
1 Mar 04, create a 10 day task: Make Terraces, select it and then Window/Split.
Now assign a Gardener from the pool to get the following view:

In the bottom pane you can
see the Effort driven box and the Task type selection.
Use the drop-down arrow to see that the Task Type can be Fixed Units (the
default), Fixed Duration or Fixed Work.

Effect
of Changes to Task Type
So let’s experiment. First
remove the Effort driven check and notice that the adjacent Previous button
changes to OK. You must click the OK button to set Project
in this new mode before changing any data – the button changing to OK,
I hope, will prompt you to remember this. With Project in the Fixed Units default
mode, try changing the Work. What happened? The Duration changes
as Project won’t change the Units as that’s what you’ve told it to
do. Now change the Duration – as you now would expect, the Work changes.
Try selecting Fixed Duration (don’t
forget to click OK before continuing) and then change the Units and
then the Work. Finally, select Fixed Work and change Units and Duration.
I think you’ll find this straightforward and Project does what you expected.
A little experimentation along
those lines shows how you can get Project to do what you want, provide you’re
aware of the formula! You will have seen that Project will not change the
element you’ve selected to be fixed.
Changes
to the Fixed Parameter
However, there’s nothing to
stop you from changing the parameter that you’ve “fixed” – the fixing is
only an order to Project not to change it. So, Project has a built-in bias
towards keeping the Units fixed if possible and then Work.
In the Garden project, reset it to the original 100% units, 10 days and 80
hours of work. Try Fixed Units, and then change the Units – you
will see that the Duration changes rather than the Work:

However, if we select Fixed Work and
then change Work, it is also the Duration changes rather than
the Units this time:

So, I'm sure as you have guessed,
if we try the final type, Fixed Duration and then change the Duration,
it is the Work that changes not the Units.

To
summarise, therefore:
Changing Fixed
Units will
adjust Duration.
Changing Fixed
Work will
adjust Duration.
Changing Fixed
Duration will
adjust Work.
To
put them all together, see the table below - I have it printed out on a card
propped up in front of me whenever I want to set up anything other than the
default effort
driven and fixed
Units.
| Work
= Resource Units X Duration |
| Field
that you change |
Field
calculated if the task is Fixed Units |
Field
calculated if the task is Fixed Work |
Field
calculated if the task is Fixed Duration |
| Work |
Duration is
recalculated |
Duration is
recalculated |
Units are
recalculated |
| Duration |
Work is
recalculated |
Units are
recalculated |
Work is
recalculated |
| Units |
Duration is
recalculated |
Duration is
recalculated |
Work is
recalculated |
Default
Setting
If you would like to change
the default parameters that Project will use, you must do this before you
enter any data. Open Tools/Options…/Schedule tab and select the Task
Type you want from the pick list and also select the box for New
tasks are effort driven. If you wish these settings to be applied,
not only to this project, but to all new projects, then click the Set
as Default button before clicking OK.

All new data entries will
then obey your settings. However, if you have already made assignments and
you want to change their settings, select all the tasks first, then enter
the changes you want in Project/Task Information…/Advanced tab. When
you click OK, the new settings will be applied "globally" to
all the selected tasks.

Remember my two prime
tips:
· Always
use the split screen technique when you have more than one resource to assign
so that you can see all the parameters and the resulting calculations that
Project makes.
· If
you run into problems, delete all the assignments from the task, select the
parameter you want Fixed click on OK to set that mode and then
reset the data to read what you want before you click
the OK button.
As
an aside, using the split screen technique is a good way to check all
your entered data when you think you've finished. Select the first task
and check the data in the bottom pane. When you're happy, click the Next button
and check the second task's data, and so on. That way you will automatically
be able to check through every task in turn. To be more sure, I usually
repeat the process, checking from the last task using the Previous button
this time. Things often look different checking from the end backwards!
Next Month
Next month we’ll have a more
detailed look at calendars and working time.
|